Welcome to our construction site page.

On this page we documented the construction of our new head office.

Background and construction planning

Our new head office with office space, repair facilities, warehouse and underground parking was built in the Massenheimer Weg in Bad Homburg, only a few hundred meters away from our previous location. The planning for the new corporate headquarters was ongoing for several years before construction even began.

After many appointments with the authorities, architects and the general contractor, the third draft was finally approved!


Nach Ausgrabung

In May 2015, the excavator finally kicked off, but not without encountering some surprises!

Before the excavator could start its work on 2,100 square meters of area, a ground survey had to be prepared. These investigations revealed that archaeological findings were suspected. Construction freeze! An archeological team came on site with rakes and brushes and dug in the scorching summer heat.

They found historic pieces of pottery from the time of the Romans, which was to be expected by the proximity to the Limes, as well as earth discolourations, which pointed to a settlement during the Celtics (up to 500 BC).

4. September 2015

The excavations are over! To celebrate, the newspaper ‘Taunus Zeitung’ (part of Frankfurter Neue Presse) has published a story on the history of our construction project so far.

Familie klein

The excavation is dredged. Pictured: Architect M. Raufenbarth, builder Ralf Pigge with wife Jutta and sons Sebastian, Johannes, Thomas and grandchild Taylor.

es geht weiter

Finally it can continue! The foundation is dredged.

sooo gross

The building will be thiiiiiis big!

Currently, it is still being investigated whether the floor can be compacted with posts or whether a thicker floor slab has to placed in order to provide the necessary load capacity. Due to this and results of the archaeological findings, the statisticians have to start all over again.

Winter

December 2015: The first snow. Winter is coming!

Stahl

February 2016: Finally it Continues.

230 tonnes of steel are processed.

Beton 1

The foundations for a stable construction are laid and the insulation is ready. Now the concrete just needs to dry.

Kellerwand

April 2016: The first walls are put up for the basement and garage. Today the weather is not playing nice as it is raining.

Kellerwaende

The basement walls are standing. Now we can finally visualise the true dimensions of our new building.

Aufzugschacht Keller

and in the middle of it all: the freight elevator!

Kellerwaende ausgiessen

April 13, 2016. The prefabricated walls are filled with concrete through the “Crab-Arms”.

Pfosten mittel

April 19, 2016 The support posts will hold the basement ceiling.

Vorbereitung Kellerdecke

June 30, 2016 Preparations for the basement ceiling are complete. Now the ceiling can come.

Kellerdecke mit TH

08. July 2016 The basement ceiling is being critically appraised by the specialists.

December 2016. View from the rear side before the winter break.

Isolierung vorne 1

August 2017: The windows are fitted and the outer insulation is in progress. Delay caused by the storm on 1 August.

The hail had destroyed 8 of the 36 automatically opening fire-safety windows on the roof!

erste Innenwand Brandschutz

As of August 2017: The first interior wall for the offices is installed.

The pink color signifies the fire resistance code F 90.

After 4.5 years of construction, our new headquarters is finally ready for move-in day.
That’s 54 months / 235 weeks / 1645 days / 39,480 hours / 2,368,800 minutes of construction!

Despite this massive time investment, over the past 7+ years (including planning) we have consistently managed to help increase sales of our dealers. What will we achieve together in the near future, now that we can put all our energy back into business activities?
Big news will follow …